Delighted to say that we are achieving great progress in 2024 with our latest Sheffield Parkway 300sqm fit out offices/warehouse project, one our latest commercial projects in Sheffield.
First Phase – Crane base installation, and commissioning of 84 warehouse lights. Completed
Second Phase – Complete office fitout to be completed in the first week March 2024, 8 days ahead of schedule.
A big thank you to all our staff, our electrical subcontractor Barlows UK and our M&E subcontractor Airflow Cooling.